Redevelopment of Bickerdike Terminal

Commenced in 2019, the project works to redevelop Bickerdike Terminal moved forward extensively in 2020. To redevelop truck accesses (fluidity and security), increase electrical capacity, replace buildings, redevelop storage areas for containers and goods, and redevelop handling areas for cruise ships, the teams carried out the following in 2020: 

  • Built new entrance on Pierre-Dupuy Avenue 
  • Installed new gatehouse 
  • Repaired underground networks (water supply, sanitary, rainwater and electrical/telecommunication)
  • Repaired railway network 
  • Redeveloped truck entrance gate 
  • Redeveloped container and cargo storage areas 
  • Built new electrical substation.